Sealed bids will be received by the Ashland Water Works & Sewer Board at Ashland City Hall, located at 83183 Hwy 9, Ashland, AL 36251, until Tuesday, October 29, 2024, at 10:00 A.M. CST, and then publicly opened and read aloud for furnishing all labor and materials, and performing all work described as follows:
SR-9 Water Main Relocation
A non-mandatory pre-bid conference will be held virtually on Tuesday, October 15, 2024, at 10:00 A.M. CST. Instructions for attending the virtual pre-bid conference are included in the contract specifications.
This project consists of:
Installing approximately 1,000 linear feet of 12" PVC water main along State Route 9 just east of downtown Ashland, AL
Following installation and connection of the proposed water main, approximately 950 linear feet of existing 12" asbestos concrete water main will be grout filled and abandoned
ESTABLISHED Net 30 Alabama Graphics Account, cash/check, or credit card to purchase this project.
Please note that some orders may be adjusted at time of delivery and/or shipping. Your invoice total may be adjusted +/- according to the destination or size of order.