22MIS04E Campus Electrical & High Voltage Repair Phase V (nr)

Installation of electrical equipment to complete Loop #3 of electrical primary 15KV system.

Status

Bidding Closed

Prebid Date 8/29/24 9:00am
Bid Date 9/5/24 2:00pm

Company & Contacts

Consulting Construction Engineering
Jamie Bailey  
205.352.2500

Location

Montevallo, AL

Documents

See Documents section above for additional bid requirements/info

Sealed proposals will be received by Coty Jones, Director of Physical Plant, University of Montevallo, Holland Floyd Physical Plant Conference Room, 75 College Drive, Station 6130, Montevallo, AL 35115 until 2:00 PM CST on September 5, 2024 for:

Phase V-Completion of Loop #3 - Conversion of Electrical Power Distribution System to 15KV

PSCA No. 012P

At which time and place they will be publicly opened and read.

A mandatory pre-bid conference will be held on August 29, 2024 at 9:00 AM CST at the University of Montevallo Physical Plant Conference Room, Station 6130, L. Holland Floyd Physical Plant, Montevallo, AL 35115: for the purpose of reviewing the project and answering Bidder’s questions. Attendance at the Pre-Bid Conference is required for all Contract Bidders intending to submit a Proposal and highly recommended for all Subcontractors. Bids from Contractor Bidders who do no attend the Mandatory Pre-Bid Conference will be rejected.

This project consists of:

  • The underground duct, installation of transformers, switches, and cabling for Phase IV completion of Loop #3.

You may use your ESTABLISHED Net 30 Alabama Graphics Account, cash/check, or credit card to purchase this project.
Please note that some orders may be adjusted at time of delivery and/or shipping. Your invoice total may be adjusted +/- according to the destination or size of order.
For assistance with this website, please contact customer service at 205-252-8505